Next Meeting:
Thursday December 7, 2000 at 11AM
Status of mpiAPI and wrapperAPI
Masha was not present at the meeting, however she sent an e-mail
indicating that she has been working with Phil to get communication b/w
mpiAPI and wrapperAPI to work. There is some problem with the code on
the C++ side. Phil and Masha have tested mpiAPI by communicating with
other programs and a test program written in Tcl which mimics the
wrapperAPI's behavior. So it is working fine. The wrapper communicates
it status to the mpiAPI, but does not receive the reply from mpiAPI.
They will continue to test this and keep the group updated of progress by
e-mail.
Status of inspiral dso
There was no progress reported here. Patrick expressed his concern that
there we were supposed to be finished construction and testing by
mid-November. We are not two weeks behind.
Status of excess power dso
Warren has been working with Martha, Rosen and Mario Diaz at Brownsville
to write the data conditioning function for the dso. It will be ready by
next week. Patrick has been coding up the rest of the excess power dso
and promised to have a working dso by next Thursday.
Any other business