Attendance:
Jolien, Ben, Mark, Stuart, Kent, Philip, Peter, Patrick, Greg,
Rauha, Warren.
Action:
1. Jolien will circulate an e-mail telling DSO authors to put the
search summary information into their DSO's
2. Stuart will circulate information about the LDAS configurations
at the sites
3. Patrick will ciruclate draft rum plan for dicussion at next
meeting.
Status of LDAS:
Riding the shock front. Freeze on 3rd June. There will be about a
week of hard testing before release is available for DSO's to test
with.
MIT LDAS has been flattened to allow fast turnaround development on
that system DSO developers can put their own DSO in a place visible
to LDAS.
E8 will use 0.2.0 of LDAS
Old passwords will continue to work up to E8. New passwords will be
needed for S1.
LDASjob package has been updated.
Status of LAL:
no problems known at the moment. Jolien will prepare the
infrastructure for release around 10 June. Testing will follow as
with last release. Duncan will back Jolien up if Jolien's new baby
comes early.
Run plan for S1:
General agreement that this should come from LSUG. The run plan
will account for the building of RDS frames in frameAPI. This run
plan will be circulated to the Upper Limit Group chairs for
discussion at their next meeting.
Next Meeting:
Thursday 6 June 2002 at 10:30 PDT.
|